Master every PMP formula with our free, comprehensive formula library. Each formula includes the equation, a worked example, and an explanation of when to use it on the PMP exam. We cover all three formula categories tested: Earned Value Management (EVM), Critical Path Method (CPM), and PERT/estimation formulas.

Expect 5-8 formula-based questions on the real exam. These are high-confidence points โ€” unlike situational questions, math questions have a single correct answer. If you memorize the formulas and practice with realistic numbers, you can bank these points reliably.

How to use this page: Start with EVM (highest frequency on the exam), then CPM, then PERT. Each formula page includes a downloadable cheat sheet version. Use our printable PMP Formula Cheat Sheet for offline review.

PMP Formulas Cheat Sheet

All the formulas you need for the PMP exam โ€” Earned Value Management, critical path, PERT, communication channels, and procurement math. Free, no sign-up. Bookmark this page.

Earned Value Management (EVM)

EV = Earned Value | PV = Planned Value | AC = Actual Cost | BAC = Budget at Completion

FormulaNameInterpretation
CV = EV โˆ’ ACCost VariancePositive = under budget
SV = EV โˆ’ PVSchedule VariancePositive = ahead of schedule
CPI = EV รท ACCost Performance Index>1.0 = under budget
SPI = EV รท PVSchedule Performance Index>1.0 = ahead of schedule

Forecasting (EAC โ€” Estimate at Completion)

FormulaCondition
EAC = BAC รท CPICurrent cost performance continues
EAC = AC + (BAC โˆ’ EV)Remaining work at planned rate
EAC = AC + [(BAC โˆ’ EV) รท (CPI ร— SPI)]Both cost and schedule performance continue
EAC = AC + Bottom-up ETCOriginal estimate is flawed

Other EVM Formulas

FormulaName
ETC = EAC โˆ’ ACEstimate to Complete
VAC = BAC โˆ’ EACVariance at Completion
TCPI = (BAC โˆ’ EV) รท (BAC โˆ’ AC)To-Complete Performance Index (budget)
TCPI = (BAC โˆ’ EV) รท (EAC โˆ’ AC)TCPI using revised EAC
๐Ÿ’ก PMP Exam Tip

You'll typically get 5-8 EVM questions on the PMP exam. You don't get a calculator โ€” all math is designed to be straightforward. Remember: CPI > 1.0 is good, SPI > 1.0 is good. TCPI tells you the efficiency needed on remaining work.

Critical Path & Float

FormulaName
Float (Slack) = LS โˆ’ ES = LF โˆ’ EFTotal Float
Free Float = ESnext โˆ’ EFcurrentFree Float (no impact on successor)
Critical Path = Longest path through networkDetermines minimum project duration

Estimating (PERT & Triangular)

FormulaName
PERT = (O + 4M + P) รท 6Beta distribution (weighted average)
Triangular = (O + M + P) รท 3Simple average
ฯƒ = (P โˆ’ O) รท 6Standard deviation (one activity)
ฯƒยฒ = [(P โˆ’ O) รท 6]ยฒVariance (one activity)

Communications & Procurement

FormulaName
Comm. Channels = n(n โˆ’ 1) รท 2Number of communication channels
EMV = Probability ร— ImpactExpected Monetary Value (risk)
PTA = [(Ceiling โˆ’ Target) รท Buyer Share] + TargetPoint of Total Assumption (FPIF only)
๐Ÿ“ฅ Free PMP Formula Cheat Sheet

Want this as a downloadable PDF? Get our Free PMP Formula Cheat Sheet โ€” includes all formulas, EVM diagrams, and example calculations.