This free PMP Formula Cheat Sheet covers every formula tested on the PMP exam. We designed it to be print-friendly (2 pages) so you can review it in the days leading up to your exam and during the parking-lot cram session before you walk into Pearson VUE.

Why Formulas Matter on the PMP

The PMP exam includes at least 5-8 formula-based questions, primarily from Earned Value Management and Critical Path Method. These are "free points" if you memorize the formulas β€” you either know the calculation or you do not. There is no situational judgment involved.

What Is Covered

PMP Formula Cheat Sheet

All the formulas you need for the PMP exam β€” Earned Value Management, Critical Path, PERT, communication channels, and procurement math. Print this page or bookmark it for exam day.

πŸ“Š Earned Value Management (EVM)

FormulaWhat It Means
CV = EV βˆ’ ACCost Variance β€” positive = under budget
SV = EV βˆ’ PVSchedule Variance β€” positive = ahead of schedule
CPI = EV / ACCost Performance Index β€” >1 = under budget
SPI = EV / PVSchedule Performance Index β€” >1 = ahead of schedule
EAC = BAC / CPIEstimate at Completion (current efficiency continues)
EAC = AC + (BAC βˆ’ EV)EAC β€” future work at planned rate
EAC = AC + [(BACβˆ’EV)/(CPIΓ—SPI)]EAC β€” both cost and schedule considered
ETC = EAC βˆ’ ACEstimate to Complete
VAC = BAC βˆ’ EACVariance at Completion
TCPI = (BACβˆ’EV) / (BACβˆ’AC)To-Complete Performance Index (original budget)
TCPI = (BACβˆ’EV) / (EACβˆ’AC)TCPI (revised budget)

πŸ—ΊοΈ Critical Path

FormulaWhat It Means
Float = LS βˆ’ ESTotal Float (Slack) = Late Start βˆ’ Early Start
Float = LF βˆ’ EFAlso: Late Finish βˆ’ Early Finish
Free Float = ES(next) βˆ’ EFFree Float β€” delay without impacting successor
Critical PathLongest path through the network. Zero float.

🎲 PERT (Program Evaluation and Review Technique)

FormulaWhat It Means
tE = (O + 4M + P) / 6Expected Duration β€” Optimistic, Most Likely, Pessimistic
Οƒ = (P βˆ’ O) / 6Standard Deviation of an activity
Οƒ(path) = √(σ₁² + Οƒβ‚‚Β² + ...)Standard deviation of a path = sqrt of sum of variances

πŸ’¬ Communication Channels

FormulaWhat It Means
n Γ— (nβˆ’1) / 2Communication channels for n stakeholders. 5 people = 10 channels.

πŸ“ˆ Procurement & Contracts

FormulaWhat It Means
FPIF: Final Price = Target Cost + Target Fee + (Actual Cost βˆ’ Target Cost) Γ— Buyer ShareFixed Price Incentive Fee
CPIF: Fee = Target Fee + (Target Cost βˆ’ Actual Cost) Γ— Seller ShareCost Plus Incentive Fee
PTA = [(Ceiling Price βˆ’ Target Price) / Buyer Share] + Target CostPoint of Total Assumption (FPIF)
Make-or-Buy: Buy if Cost(buy) < Cost(make)Simple cost comparison

πŸ’‘ Exam Tips

Want all 35 ECO tasks explained? Get the complete study guide.

View All Products